Core Network Upgrades - Week 3
Closed
Planned
Event Created: 13/07/2021 16:59:17
Event Closed: 05/08/2021 00:09:07
Scheduled Start -
Scheduled End -

As part of our ongoing commitment to stability and performance of our network, we will be performing software updates across our core network estate spread over the next three weeks. This work will require an outage of around 45 minutes per device. Resilient devices in each site will be upgraded during separate windows to minimise impact across the network. Customers with resilient circuits, or consuming services in other sites should not see any impact to their service. However, all services will be considered at risk for the duration of the window. Vorboss has taken all steps to mitigate the outage during the maintenance window. Customer with non-resilient services will see an impact to their services within the sites included in the provided windows. The service maintenance will be conducted between 21:00 UTC and 02:00 UTC for the sites and dates listed below: Window 9 - 01/08/2021 GB/HRL01 (Harlow - Kao Data) GB/LON01 (London - LDeX 1) Window 10 - 02/08/2021 GB/LON02 (London - Telehouse Docklands) GB/LON06 (London - Volta Data Centres) Window 11 - 03/08/2021 GB/LON07 (London - Interxion LON1) GB/LON09 (London - Equinix LD8) GB/LON10 (London - Virtus London 1) Window 12 - 04/08/2021 GB/LON08 (London - Equinix LD4) GB/STV01 (Stevenage - ServerChoice SC-1) We will update this maintenance ticket prior to commencing works in each site and will update again once complete. If you are unsure if your service is affected during the maintenance window, or have any other queries please raise a ticket via our support portal.

Latest Updates

02/08/2021 22:24:32
GB/LON02 has been given the all clear, GB/LON06 will be going down for maintenance shortly.
03/08/2021 22:12:23
GB/LON07 has been given the all clear, GB/LON09 will be going down for maintenance shortly.
03/08/2021 00:11:51
GB/LON06 has been given the all clear. This concludes our work on Window 10. We will post a further update before we begin the first site for Window 11.
05/08/2021 00:09:07
GB/STV01 has been given the all clear. This concludes our work on Window 12. This concludes the this week's upgrades.
03/08/2021 20:59:05
Our Window 11 maintenance is now beginning. GB/LON10 will be going down for maintenance shortly, we will announce our all-clear for this site once complete along with the next site announcement.
03/08/2021 21:17:29
GB/LON10 has been given the all clear, GB/LON07 will be going down for maintenance shortly.
02/08/2021 00:16:29
GB/LON01 has been given the all clear. This concludes our work on Window 9 and this week's maintenance notification.
02/08/2021 20:59:25
Our Window 10 maintenance is now beginning. GB/LON02 will be going down for maintenance shortly, we will announce our all-clear for this site once complete along with the next site announcement.
04/08/2021 21:32:41
GB/LON08 has been given the all clear, GB/STV01 will be going down for maintenance shortly.
04/08/2021 00:36:31
GB/LON09 has been given the all clear. This concludes our work on Window 11. We will post a further update before we begin the first site for Window 12.
01/08/2021 21:00:01
Our Window 9 maintenance is now beginning. GB/HRL01 will be going down for maintenance shortly, we will announce our all-clear for this site once complete along with the next site announcement.
01/08/2021 22:53:14
GB/HRL01 has been given the all clear, GB/LON01 will be going down for maintenance shortly.
04/08/2021 21:02:03
Our Window 12 maintenance is now beginning. GB/LON08 will be going down for maintenance shortly, we will announce our all-clear for this site once complete along with the next site announcement.