Core Network Upgrades - Week 3 (SN-20210713-3)

Created 3 weeks ago, Last updated 4 hours ago.

Issue Summary

As part of our ongoing commitment to stability and performance of our network, we will be performing software updates across our core network estate spread over the next three weeks. This work will require an outage of around 45 minutes per device.

Resilient devices in each site will be upgraded during separate windows to minimise impact across the network.

Customers with resilient circuits, or consuming services in other sites should not see any impact to their service. However, all services will be considered at risk for the duration of the window. Vorboss has taken all steps to mitigate the outage during the maintenance window.

Customer with non-resilient services will see an impact to their services within the sites included in the provided windows.

The service maintenance will be conducted between 21:00 UTC and 02:00 UTC for the sites and dates listed below:

Window 9 - 01/08/2021

  • GB/HRL01 (Harlow - Kao Data)
  • GB/LON01 (London - LDeX 1)

Window 10 - 02/08/2021

  • GB/LON02 (London - Telehouse Docklands)
  • GB/LON06 (London - Volta Data Centres)

Window 11 - 03/08/2021

  • GB/LON07 (London - Interxion LON1)
  • GB/LON09 (London - Equinix LD8)
  • GB/LON10 (London - Virtus London 1)

Window 12 - 04/08/2021

  • GB/LON08 (London - Equinix LD4)
  • GB/STV01 (Stevenage - ServerChoice SC-1)

We will update this maintenance ticket prior to commencing works in each site and will update again once complete.

If you are unsure if your service is affected during the maintenance window, or have any other queries please raise a ticket via our support portal.

Need Help?

If you believe that your services have been affected by this incident, please raise a support ticket online at https://secure.vorboss.net

If the matter is urgent you may also contact the Vorboss Network Operations team on per the knowledge base page KB15052001

Issue Updates

Please note that these updates are in reverse order (most recent updates first).

00:11 UTC today

GB/LON06 has been given the all clear.

This concludes our work on Window 10. We will post a further update before we begin the first site for Window 11.

22:24 UTC yesterday

GB/LON02 has been given the all clear, GB/LON06 will be going down for maintenance shortly.

20:59 UTC yesterday

Our Window 10 maintenance is now beginning.

GB/LON02 will be going down for maintenance shortly, we will announce our all-clear for this site once complete along with the next site announcement.

00:16 UTC yesterday

GB/LON01 has been given the all clear. This concludes our work on Window 9 and this week's maintenance notification.

Sunday 1 August at 22:53 UTC

GB/HRL01 has been given the all clear, GB/LON01 will be going down for maintenance shortly.

Sunday 1 August at 21:00 UTC

Our Window 9 maintenance is now beginning.

GB/HRL01 will be going down for maintenance shortly, we will announce our all-clear for this site once complete along with the next site announcement.